Office Fit-Out Budget: Compare the Scope Before the Rate
AI-generated representative visual. The worksheet is a proposed buyer tool, not an IBS quotation or a completed client budget.
An office fit-out budget needs a stated scope before a rate can be compared. Record the area basis, existing shell, design issue, package boundaries and costs retained by the client. Then identify which figures are supported, assumed or still awaiting a decision. This proposed worksheet helps architects, PMCs and procurement teams prepare that review. It contains blank fields, with no IBS price, standard rate or recommended allowance percentage.
Download the blank scope worksheet
Use one row for a cost line or unresolved scope decision. Start with a project reference, location, review date and estimate revision. Keep drawings, quotations and surveys in your project folder; enter their references so another reviewer can find the basis without guessing which file was used.
The CSV has no formulas or prefilled prices. Agree the cost categories, approval authority and review status with your cost consultant or project team. Add rows for your actual package. Leave an unpriced line visible and name the person who will resolve it; a blank amount must not quietly become a zero in the comparison.
Put the area and shell condition beside the amount
Write down the area used, its unit and its source. Identify whether it describes the tenant work area, a lease figure or another measured boundary. If bidders use different areas, request a reconciliation before comparing a rate per square foot. Retain the original quantities rather than overwrite them with a preferred denominator.
Attach the landlord handover list and survey reference. Mark the ceiling, floor, HVAC, electrical and fire-service elements that exist, need alteration or require confirmation. Bare shell, warm shell and Cat A/Cat B labels can appear in briefs, but your itemised handover list must explain the actual starting condition.
Use the comparison to expose a missing appointment
A bidder may price installation while the client expects design, equipment supply and testing too. Review those boundaries separately. Identify the architect, services consultants, landlord contractors and specialist suppliers already appointed, and show the work retained by each.
The table below is a proposed decision aid. Its purpose is to turn a difference between two offers into a question with an owner. It does not allocate design liability or approval responsibility on behalf of the parties.
| Budget line | Information to compare | Decision or record required |
|---|---|---|
| Civil and retained work | Strip-out, protection, making good and existing-condition assumptions | Survey reference and boundary accepted by the project team |
| MEP and equipment | Design, supply, installation, landlord interfaces and testing | Named appointment and relevant equipment/services schedule |
| Furniture and branding | Custom manufacture, bought-in items, graphics and installation | Item quantities, approved specification and procurement route |
| Design and client-retained costs | Consultants, application support, client purchases and relocation | Included or separately carried, with a cost owner |
| Allowances and open decisions | Reason, evidence, unresolved scope and review date | Named owner, treatment in the review total and next decision |
Use your contract and appointed technical team to settle responsibilities. A comparison entry is not an approval to proceed.
Keep client-retained costs visible
RICS NRM 1 separates building-work costs, project/design-team fees and other project costs, with risk and inflation identified separately. That is useful cost-planning guidance for a clear breakdown. Agree the classification for this office with the appointed cost team, including the currency, estimate date and treatment of tax.
Check whether an item is already inside another amount before adding it. Furniture in the contractor’s BOQ must not also remain as an unexplained client allowance. Conversely, a client-purchased access-control system still needs an identified cost owner and installation interface even when its purchase sits outside the fit-out tender.

Give every allowance a reason and a review date
An allowance should point to a question: an unavailable landlord record, an undecided finish or a design detail awaiting review. Enter the amount only when its basis has been assessed, with the decision owner and the action needed to replace the assumption. Separate this from a known item that simply has not received a quotation.
RICS NRM 1 bases risk allowances on an assessment of project uncertainty rather than standard percentages. The blank worksheet therefore proposes no contingency rate. Ask the cost team to record how an allowance relates to the unresolved condition and how that condition will be reviewed as information improves.
Issue the same revision, then retain the decision trail
Before inviting comparable bids, review the open-decision column with the client, architect and PMC. Issue the same drawing register, item schedule, assumptions and return format to each bidder. Request that departures and exclusions are identified against the relevant line, with any design or programme effect stated.
Keep a dated copy when the scope is approved for the next stage. Later changes need a new decision reference rather than an overwritten cell. IBS can review office execution with its in-house teams and furniture manufacture near Vasai East; the proposed appointment determines design, specialist and liaison responsibilities. Send the drawings, location, area and target date with your enquiry so the scope review starts from the same brief.
Sources
- NRM 1 separates base-cost components from risk/inflation and relates risk allowances to assessed project uncertainty. Used as technical cost-planning guidance, without adopting its tax context or setting Indian rates. RICS, NRM 1, October 2021 edition reissued October 2022, sections 2.4 and 3.18; read 25 November 2026
Frequently asked questions
What should an office fit-out budget worksheet include?
Can I use one rate per square foot to compare contractors?
Does the download calculate a fit-out price?
How should we treat a missing quotation or blank amount?
Should design and landlord approval work be included?
Who approves the budget before a tender is issued?
What should we send IBS for an office fit-out review?
Have an office scope to review?
Send the drawings or available plan, location, area and target date. Include the shell handover list and whether your architect or PMC has issued the design.