ACP Cladding BOQ Checklist: Panels, Submittals and Facade Interfaces

VB
Vishal Barot
Co-Founder & CEO
7 min read

AI-generated representative visual. The scene illustrates the subject and is not a photograph of a named IBS project.

An ACP cladding BOQ should identify the proposed aluminium composite panel and the complete work needed to install it. Record the approved panel product, finish, quantities, substructure and fixing responsibilities, adjoining interfaces and access scope. Compare quotations against that package. The architect and responsible project engineers must approve design and product suitability before fabrication; a square-foot panel rate alone leaves important decisions unresolved.

Draw the cladding boundary before measuring it

Mark the facade elevations, column wraps, fascia, soffits and returns included in the package. Identify retained work and areas requiring dismantling. Give the BOQ a drawing register and revision so every bidder measures the same scope. Record how openings, edges and returns are measured under the agreed rules.

List adjoining work on the same elevation: glazing, entrance doors, signage, lighting and service penetrations. A finish line on an architectural drawing can be an interface between several contractors. Name who supplies each supporting component and who closes the junction before comparing panel rates.

Use the BOQ to expose package interfaces

The table is a procurement checklist. It asks what must be defined and approved; it does not specify structural members, anchors, spans or a facade design. Include the responsible designer and reviewer in the tender return so assumptions have a clear route to resolution.

ACP facade BOQ: scope and approval checklist
BOQ componentDefine for comparable pricingApproval / interface record
ACP panelsManufacturer, exact product, core, thickness, coating and finishMaterial submission and approved sample reference
Set-out and fabricationElevations, panel joints, folds, returns and opening scheduleApproved drawing revision and fabrication release
Substructure and fixingsResponsible designer; included supply and installation scopeEngineer-approved details and inspection requirements
Signage and lightingMounting, supports, access and electrical responsibilitiesCoordinated sign / lighting drawing
Glazing and other junctionsPackage boundary, closure and sealing responsibilitiesAgreed interface detail and reviewer
Access and removalWork windows, access equipment, dismantling and disposalClient site arrangements and priced inclusions
CompletionInspections, snag closure and retained product recordsAcceptance, maintenance and warranty documents

Add quantities, measurement units, rates, tax treatment and explicit exclusions. Product selection and engineered details require project approval.

Request a product-specific material submission

The submission should name the manufacturer and the exact panel product, its declared build-up, coating and finish, and the documents required by the project specification. Keep the sample code with the drawing and procurement records. If an alternate is proposed, identify every difference for the architect and technical reviewers.

TECNALIA’s April 2026 assessment announcement for specified Aludecor products discusses reaction-to-fire and mechanical testing. It is an example of product-specific performance assessment. It does not show that all ACP products share those characteristics or that a particular facade application has project approval.

Keep core and fire-performance evidence tied to the proposed product

Ask for the evidence required by the project’s fire and technical reviewers, matching the actual panel product and relevant tested construction. Give them the report, scope and stated limitations. A colour sample cannot answer a performance question, and the term “ACP” does not identify one core or one test result.

The responsible specialists must decide which evidence is applicable to the proposed use and the full facade arrangement. Record their decision before procurement. This checklist assigns no universal fire class and offers no blanket claim that ACP is fireproof or suitable for every commercial building.

Representative entrance facade with metal-faced cladding around columns, soffit and glazing
Representative completed facade visual. The checklist does not describe the design or performance of this illustrated building.

Resolve the sign and lighting interfaces before closing panels

A fascia may also carry letters, a sign box or lighting. Show the approved mounting locations and allocate supports, cabling, access and final connections. Keep electrical work with the responsible trade under the agreed scope. Changes after panel fabrication should return through the drawing and commercial approval process.

Capture access restrictions and operating hours in the quotation. Installation at an occupied branch or showroom needs a site-approved method and work window. Include protection of retained finishes, removal of existing signs and responsibility for making good. These are scope decisions, not interchangeable additions to a bare panel supply rate.

Release fabrication against the approved set

Before release, reconcile the drawing revision, site measurements, material sample and approved technical submissions. The fabrication list should identify where each panel or assembly belongs. Record any unresolved interface instead of treating a tender assumption as a completed design decision.

IBS fabricates ACP cladding elements in-house and can scope the agreed installation with its civil and signage teams. For handover, retain the accepted product references, drawings, inspection records, snags, maintenance information and warranty terms. Send IBS the elevations and BOQ for a defined package proposal, with open design and approval items identified.

Sources

Frequently asked questions

What should an ACP cladding BOQ include?
Define the panel product, finish and measured areas together with fabrication, returns, substructure, fixings, junctions and installation responsibilities. Include access equipment, removal and handover where required. Attach the drawings and measurement rules so bidders price the same package rather than different interpretations of a square-foot rate.
Is ACP cladding fireproof?
A blanket description is not an adequate product specification. ACP products differ in construction and declared performance. The project’s responsible fire and technical reviewers must assess the actual product evidence and proposed use. Request the specified reports and their scope instead of accepting a general marketing claim.
Who approves the cladding fixing and support details?
The project must identify the responsible designer and approving engineer for the substructure, anchors and fixings. Their approved details should control fabrication and installation. This article provides procurement questions, not structural design. Ask the tender team to state the design and review responsibilities before award.
Can the ACP and signage packages be combined?
Yes, the procurement scope can include both where the responsibilities are defined. Coordinate sign locations, supports, access, cabling and final connections on the approved drawings. IBS has in-house cladding fabrication and signage capabilities. The quotation should state the interfaces and the work included in each trade.
What is needed to compare two ACP quotations?
Use the same drawing revision, panel product specification, measurement rules and installation scope. Check the inclusions for supports, returns, openings, access and removal. Review technical departures separately. A lower panel rate may cover a different product or package, so compare the complete defined scope.
What should we send IBS for an ACP facade quotation?
Send the site location, elevations, BOQ or measured scope, material specification and available engineering details. Identify signage, glazing and service interfaces, access restrictions and target dates. List any design or approval items still open so IBS can clarify its fabrication and installation proposal against the agreed scope.
VB
Vishal Barot
Co-Founder & CEO, Impulse Branding Solutions

Vishal leads Impulse Branding Solutions, a Mumbai-based manufacturer and commercial fit-out contractor. IBS combines in-house print and signage production with civil, MEP, interior and furniture execution across India.