Hotel Fit-Out Tender Checklist: Mock-Up Rooms, MEP Interfaces and Phased Handover
AI-generated representative hotel interior. Not a photograph of an IBS hotel project.
A hotel fit-out tender should tell every bidder what to build, whose approval is required and when a room or floor can be released. Issue the drawing register, BOQ, specifications, package responsibilities and working constraints together. For an operating hotel, add guest separation and service shutdown arrangements. This is IBS’s proposed checklist for an architect-led package, to be adapted to the owner’s contract and operator requirements.
Issue a package that can be priced against one revision
List the rooms and common areas included, identify repeat room types and mark what remains outside the contract. Issue the architectural and services drawings with their revision dates. Good for construction, or GFC, means the approved drawing set intended for execution; do not mix it silently with an earlier tender layout.
Include room data sheets, finish schedules, quantities, approved makes and the tender return format. Identify design questions before award. A bidder should show its assumptions and exclusions in one place so the architect and quantity surveyor can compare offers against the same scope.
Make the interfaces visible in a responsibility matrix
Assign supply, installation, connections, testing and approval separately where different parties own them. The table is a discussion template, not a default allocation of liability.
| Interface | Settle in the tender | Release evidence |
|---|---|---|
| Civil and wet areas | Setting-out, substrate, waterproofing and access panels | Approved detail and inspection record before closing |
| MEP and ceilings | Mechanical, electrical and plumbing routes; openings and access | Coordinated drawings and agreed tests |
| Fire and life safety | System interfaces and the responsible specialist / reviewer | Required approvals and commissioning records |
| Joinery and services | Factory dimensions, power points, hardware and fixing details | Approved shop drawing, sample and site measurement |
| FF&E and finishes | Furniture, fixtures and equipment supply; installation and protection | Item schedule and room readiness sign-off |
| Signage and wayfinding | Operator artwork, room numbering and mounting positions | Approved sign schedule and installation check |
Name the owner, architect, PMC, operator and contractor decision-makers for each interface. Approval responsibilities follow the appointment and contract.
Use the mock-up room to settle details before repetition
Define what the mock-up must demonstrate: finished dimensions, joinery, lighting controls, sockets, bathroom details, access for maintenance and furniture clearances. State who reviews it and how comments become a signed record. An approved material swatch does not approve an entire assembled room.
Keep the approved room and its drawing revisions as the reference. Before repeating it, resolve deviations and record any operator changes. Separate approval to fabricate an item from approval to install it at site. That distinction matters when joinery production and services work run at the same time.
Approve the shop drawings and samples before factory release
A shop drawing translates the design into fabrication and fixing details. For a wardrobe or reception counter, check dimensions, materials, edge details, hardware and service interfaces. Name the sample or prototype required and the approval date needed to protect the programme.
IBS makes furniture at its factory near Vasai East and executes civil, MEP and interior work through its own teams. On an architect-led assignment, the architect’s design remains the reference. Proposed substitutions should arrive as identified alternatives for approval, with the cost and programme effects stated.

Price an operating hotel around access and service windows
Agree the work zones, guest routes, material entry, waste removal and storage before mobilisation. Record permitted noise-producing work and the party authorising shutdowns. Isolate work areas and protect retained finishes using a method agreed with the property team.
The tender should say who releases rooms, who confirms services can be interrupted and how a delayed release changes the sequence. A programme based on vacant floors is not comparable with a programme for occupied rooms. Price the actual operating constraints, including repeated mobilisation where the package requires it.
Check the execution evidence and property onboarding requirements
Request completed-work records relevant to the proposed trades, key staff, manufacturing capability and quality and safety procedures. Check which legal entity delivered each reference. IBS’s confirmed work includes GroupM’s Mumbai office and airport interior and branding assignments; WeWork Mumbai work is attributed to sister company RKS Interior Pvt Ltd.
Operator requirements also matter. IHCL’s published supplier framework describes contractor safety documentation and checks on insurance. It is an example of one operator’s process, not a universal hotel checklist. Obtain the actual property requirements and confirm what documents must be accepted before work starts.
Record changes before they disappear into the next room
Give each request for information a drawing reference, owner and required response date. For a variation, record the reason, quantity, rate basis and effect on sequencing. Agree the authority that can approve it. A site instruction and an approved commercial variation may be different records under the contract.
Release completed areas in the agreed sequence. Before the next trade enters, record the inspection and protection responsibilities. Photographs help, but they do not replace a signed measurement or an agreed test result.
Define what makes a room ready for handover
Agree the room or floor checklist before work begins: installed items, testing, snag status, cleaning, keys, operation manuals, warranties and as-built records. Name who accepts the area and which defects prevent release. Track remaining items separately from the completion record.
For an invitation to price, send IBS the location, drawing register, BOQ, package scope, room or area schedule and working constraints. Include the required handover dates. IBS can review the execution package without taking over the appointed architect’s design role.
Sources
- IHCL describes its contractor safety programme, including documentation and insurance checks. Requirements are operator-specific. IHCL, Partner Transformation supplier framework
- The Council of Architecture publishes guidance on architectural appointments and professional contracts; roles must follow the project appointments. Council of Architecture, Manual of Architectural Practices
Frequently asked questions
What documents are needed for a hotel fit-out tender?
Why include a mock-up room in the fit-out scope?
Can a hotel remain open during fit-out work?
Can IBS work under our appointed architect or PMC?
Have an architect-issued hotel package?
Send the drawing register, BOQ, location and working constraints. IBS can review the execution scope for your tender.